SPOR designed, supplied, installed and commissioned a fully integrated AV solution for a 27,000 sq ft sixth-floor fit-out on The Strand, London.
AV was planned alongside the main construction programme and the client's IT from the start, so boardrooms, meeting rooms and hybrid spaces were ready on day one.
CLIENT
Recruitment Agency
LOCATION
The Strand, London
PROGRAMME & SIZE
12–16 weeks,
27,000 sq ft
PROJECT
6th floor AV
fit-out

THE CHALLENGE
WHAT NEEDED
TO CHANGE
The client needed a high-performance collaboration environment for its new sixth-floor workplace, aligned with modern workplace standards and fitting seamlessly into the wider construction programme and IT infrastructure.
01
02
03
Deliver AV within a live construction programme
No impact on the main contractor's completion milestones
Secure, scalable AV-over-IP built with the client's IT team
THE SOLUTION
WHAT WE
DELIVERED
SPOR ran structured design workshops, then delivered Microsoft Teams Rooms with PTZ cameras, Shure MXA910 ceiling microphones and DSP, and touch control. Racks were built and tested off-site, and commissioning was staged to cut on-site time and risk.
01
DESIGN
Design workshops shaped every room around how the team meets, from huddles to boardrooms.
02
INTEGRATE
Video conferencing, Shure audio and AV-over-IP, integrated with the client's IT infrastructure.
03
INSTALL
Racks built off-site, then installed and commissioned in line with the construction programme.